Subject |
Member |
Finish Time |
|
|
1 |
Research |
|
10/5 |
|
l Lens |
Abhay |
||
|
l Mechanical |
All members |
||
|
l PLC setting |
Yang Kerem |
||
|
l PLC-PC connecting |
|||
|
l PLC programming |
|||
|
l Remote internet commanding |
|||
|
l Feedback control system |
|||
|
2 |
Design the lens and machine |
All members |
10/15 |
|
3 |
Submit process plan |
|
10/23 |
|
l Lens |
Abhay |
||
|
l Mechanical |
Josh, Kerem |
||
|
4 |
Buy the components |
Josh |
11/6 |
|
5 |
Initial manufacturing |
All members |
11/6 |
|
6 |
Build the machine |
11/6 |
|
|
7 |
Test lens , machine, and integration of PLC and PC |
11/25 |
|
|
8 |
Final design |
11/30 |
|
|
9 |
Do a final manufacturing run until we get a good part |
12/1 |
|
|
10 |
Final test |
12/1 |
|
|
11 |
Project report |
12/1 |
|
|
12 |
Web design and update |
12/6 |
|